Water Transport & Networks

Since its establishment in 1975, Astraco has successfully delivered hundreds of projects across a wide range of sectors. Our portfolio includes major infrastructure works, such as potable water networks, sewerage systems, and stormwater networks, as well as industrial facilities, commercial buildings, hotels, and residential developments.

List of Projects

Our major prestigious completed projects in this industry is shown below

Main RW Pipelines, Installation of Chambers and Miscellaneous System Improvement/Modification works at Different Areas in Al Ain Region Contract No: A-19798

The scope of covers the procurement and supply of materials, delivery, transportation, handling, storing at site, surveying of the site, detailed design, preparation of technical submittal for materials and equipment, preparation of shop drawings, constructions, erection, installation testing, commissioning, new development/replacement, replacing pipeline and other installation by new provision where necessary. Upgradation of pump stations at 4 locations. New development /replacement of old existing pipeline and associated works LM DI/HDPE pipe line DN 150 to DN 600 including NDRC and associated electrical installation works

Client / Consultant –TAQA, Location – UAE, Year of Completion – Ongoing,

3 Years Blanket Agreement of Pipeline Repair Works in All Transco Regions Contract No: N-19622/C

The scope of work consist of repairing or replacement of leaking pipeline in Transco regions, the work comprises any emergency & urgent site inspection and mobilization of manpower, equipment & machinery, material, etc. to repair or to replace a certain defected section of water transmission main pipeline in Transco network / pump stations: suction & Discharge Headers / Piping on emergency basis in coordination with water maintenance engineer.

Client / Consultant –TAQA, Location – UAE, Year of Completion – Ongoing,

Blanket Agreement for Pipeline Repair Activities in All Regions of UAE (3 Years) Contract No: N-18506C

The work comprises of the urgent site inspection and mobilization of manpower, equipment, material etc. to repair or to replace a certain defected section of water transmission main / Pump Suction & Discharge Headers/ Piping on emergency basis in coordination with Water Transmission Engineer. The emergency response contract includes the Water Transmission mains in the Abu Dhabi Island, Mainland, Eastern Region, Western Region and Fujairah.

Client / Consultant –TRANSCO, Location – UAE, Year of Completion – 2024,

EPC Contract for Al Ain Water Transmission Scheme (AWTS) Pipeline from AI Hayer Tanks Compound to Junction ‘A' IP131 Area at Al Ain and Pipeline from Zakher Pumping Station to Mezyad Contract No. N4381B

Engineering, Procurement and Construction of 42.7 K.M. DN 1600 D.I. Pipeline, 4.7 K.M. DN 1400 D.I. Pipeline with 6.8 K.M. 8 branches of DN 400 to DN 1200 from AI Hayer Tanks Compound to Junction A, lP131 Area of AI Ain. & 22.0 KM DN 1600 Ductile Iron Pipeline with 4.0 K.M. five branch lines of DN 800 and DN 1000 from Zakher to Mezyad including Electrical and Scada Control System.

Client / Consultant –TRANSCO /Tebodin Middle East Ltd, Location – Al Ain, Year of Completion – 2020,

Three (3) years LTPA for Repair Works of Existing Transmission Pipelines at Abu Dhabi and Eastern (AI Ain) Regions

Attend the site and assess damage up on receiving information about any defect or incident (leakage or pipeline damage of any anature) with TRANSCO Engineer. Communicate and agree the methods of repair. Acquire all required security passes from other utility owners. Mobilize immediately to site and commence the repairing works

Client / Consultant –TRANSCO, Location – UAE, Year of Completion – 2018,

Urgent Works at AARS, Sarouj, Khabaisi and Hilli Pumping Stations Contract No. N-3232

Construction of 1300 meters DN 1200 carbon steel pipeline interconnection including motor operated valves, check valves, flow control valves, construction of 2000 meters DN 1200 D.I. pipeline including flow control valves, butterfly valves, various connections to existing reservoirs, pumping stations, etc, all associated civil works including electro mechanical works including Scada System, flow meters, modification to existing electrical system, etc.

Client / Consultant –TRANSCO /Tebodin Middle East Ltd, Location – Al Ain, Year of Completion – 2010,

Supply and Installation of Water Meters in Abu Dhabi Region Lot A&B Contract No. D 5391

Supply and installation of 121,800 Nos Electronic Consumer Water Meters (Size: 1/2″ to 2″) instead of existing mechanical water meters including complete survey works, supply and installation of Induction Touch Pad, Hand Held Remote Reading Device, Check Valve, Stop Valve, Lockable Brass Valves and various types of pipe fittings.

Client / Consultant –ADDC /Hyder Consulting, Location – Abu Dhabi Region, Year of Completion – 2007,

Completion of Outstanding Works for the Terminated Contract No. N-00-0302 Contract No. N-2917

Installation of 5.1 KM DN 900 mm Ductile Iron Pipeline, construction of chambers, transportation of free supplied pipes & fittings, exhume existing pipes, repair and transport to Client’s store.

Client / Consultant –ADWEA /Penspen International Ltd, Location – Mussafah Abu Dhabi Region, Year of Completion – 2006,

DN 1000 Irrigation Pipelines from Sweihan to AI Maha Forest and Ajban Farms (Bida Khalifa) Contract No. N1919

Construction and Commissioning of 122.0 KM DN 1000 Pipelines, from Sweihan to Al Maha Forest and Ajban Farms including connections to existing reservoir inlets and outlets, construction of chambers, thrust blocks and all other associated civil works, electro mechanical works, Scada control system, etc.

Client / Consultant –ADWEA /Montgomery Watson, Location – Ajban Abu Dhabi Region, Year of Completion – 2006,

DN 1200 Transmission Pipeline No.3 From Taweelah to Unit III C ontract No. G 1403

Supply, installation, testing and commissioning of 36.0 KM DN 1200 Ductile Iron Pipeline from Taweelah to Unit III Pumping Station including

connection and disconnection to the existing DN 1200 and DN 1000 Pipeline, construction of chambers and associated civil works including modification to Scada Software, PLC Control System with related electro mechanical works.

Client / Consultant –ADWEA /Tebodin Middle East Ltd, Location – Tawaleeh Abu Dhabi Region, Year of Completion – 2005,

Seih Garaba Well Water Transmission Scheme Contract No. G-1191

Water Transmission Network from Seih Gharaba Water Wells to existing water tanks consisting of approx. 28.0 KM of pipeline of DN 500 mm GRP and DN 300 mm Ductile iron pipe, including chambers, well houses, control room building, electro mechanical works, Scada and Control System, deep well pumps, etc.

Client / Consultant –ADWEA /Tebodin Middle East Ltd, Location – Seih Gharaba AI Ain, Year of Completion – 2004,

Improvement of Water Supply toAI Jazeera Hotel, Ghatoot Palaces and Bungalows Contract No. G-1171

7.0 KM DN 300-500 mm Ductile Iron Water Distribution Network at AI Jazeera Area including connections to existing tanks and network systems, construction of chambers, formation of embankment, etc.

Client / Consultant – Abu Dhabi Water & Electricity Authority, Location – Ghantoot Abu Dhabi, Year of Completion – 2004,

AI Yaif Well Water Transmission Scheme Contract No. G-1176

Water Transmission network from AI Yaif Water Wells to Sh. Mansour Tank, AI Naggi Tank and Al Azab Tank consisting of 63.5 KM of 400 mm dia GRP and OD 450, 315 & 180 HDPE Pipeline from Bida Saif to Sh. Mansour Tank and Backup line from existing DN 100 to 400 Ductile Iron pipe water line, connection to VIP/VVIP at AI Ain Areas including 18 Nos well houses, pumping station, reservoir, accommodation building, external works inside Pumping Station compound with electro mechanical works, Scada Control System, etc.

Client / Consultant – Abu Dhabi Water & Electricity Authority /Tebodin Middle East Ltd., Location – AI Yaif AI Ain, Year of Completion – 2004,

Water Supply to 650 Farms in Bahya & Connection on DN 600mm Pipeline near Al Bahya Contract No. G1066

4.0 KM of 500 mm dia Water Supply Scheme, connection of existing 600 mm dia pipeline with all associated chambers, thrust blocks, etc.

Client / Consultant –ADWEA /Tebodin Middle East Ltd., Location – Tawaleeh, Year of Completion – 2003,

Water Supply to House Complexes at Sadar Contract No. D-01-0024

17.0 KM of 200mm, 300mm & 600mm Dia Water Supply Scheme including channel crossing to Sh. Saif Island, connection to existing 1000 mm dia pipeline with all associated chambers, thrust blocks, etc

Client / Consultant –ADWEA, Location – Tawaleeh, Year of Completion – 2003,

Water Supply to House Complexes at Sadar Contract No. D-01-0024

17.0 KM of 200mm, 300mm & 600mm Dia Water Supply Scheme including channel crossing to Sh. Saif Island, connection to existing 1000 mm dia pipeline with all associated chambers, thrust blocks, etc

Client / Consultant –ADWEA, Location – Tawaleeh, Year of Completion – 2003,

Water Distribution System in AI Ain Area Contract No. A-99-0031

Water Distribution Network at Towayya, Masoudi,Falaj Hazza, Markhania, Al-Oha, Ramlat AI Rae and Al Faqa. 360.0 KM 150-600 mm dia Ductile Iron Pipeline including house connections, NDRC, 0.5 m Gallon Reservoir, pumping station, connection to existing pipelines, electro mechanical works, etc.

Client / Consultant –ADWEA/Tebodin Middle East Ltd., Location – Al Ain, Year of Completion – 2002,

AI Shabak Water Project Contract No. A-99-0024

47.0 KM 100-600 mm dia Ductile Iron Pipeline, Valve Chambers, Manholes, NDRC, etc.

Client / Consultant –ADWEA/Mott MacDonald, Location – Al Ain, Year of Completion – 2001,

Water Distribution Network at Towayya Contract No. A-99-0118

5.0 KM 100-600 mm dia Ductile Iron Pipeline, Valve Chambers, NDRC, house connections, augmentation and maintenance, etc.

Client / Consultant –ADWEA /D.Balfour & Sons, Location – Al Ain, Year of Completion – 2001,

Water Pipeline for Al Wirsan Water Tank in Ajban Area Contract No. ADWEA/WD/AD- 286/98

5.0 KM 200 mm dia Ductile Iron Pipeline, Valve Chambers, connection to existing water tanks, etc.

Client / Consultant –ADWEA, Location – Abu Dhabi, Year of Completion – 1999,

Water Supply to AI Maquam Palace Contract No. ADWEA/WD/AA- 281/98

43.35 KM 100mm – 800mm dia Ductile Iron Pipeline, Reservoir, Augmention & Maintenance Works and House Connections.

Client / Consultant –ADWEA/D.Balfour & Sons, Location – Al Ain, Year of Completion – 1999,

Water Supply Line for New Jurf Palace Contract No. ADWEA/AD/WD- 283/98

Supply and Construction of 300 mm Dia 6.0 KM Supply Line for New Jurf Palace

Client / Consultant –WED, Location – Abu Dhabi, Year of Completion – 1999,

Water Trunkmain From Taweelah to Pipeline Parallel to Abu Dhabi-Dubai Road Contract Nos: WED/VWD-541/95 & WED/VWD-542/95

Installation of Ductile Iron Pipes, Fittings & Valves, 1000 mm Dia 28.5 KM, 500mm Dia 5.7 KM, 4 Nos NDRC, gatch protection bond, valve chambers, including all associated works.

Client / Consultant –WED/Tebodin Middle East Ltd, Location – Tawaleeh, Year of Completion – 1998,

Water Transmission Lines From & To Tanks at Hilli, Etc. Contract No. WE-21

Construction of 77.3 KM 300mm to 1200mm dia Ductile Iron Water Supply Pipeline, 2m to 15m deep, valve chambers, 1500 metres NDRC at AI Ain, Hilli, Markhania, Khabisi Areas

Client / Consultant –WED/D.Balfour & Sons, Location – Al Ain, Year of Completion – 1998,

Water Transmission Line from Shuwaib to Al Feeli Wadi Contract No. H-12

Construction of 41.0 KM 500mm Dia Water Supply Pipeline, 1 No. 1 Million Imp. Gallon Concrete Tanks, 2 Nos Pumping Station and Electro Mechanical Works at Feeli / Shuwaib Area

Client / Consultant – Al Ain Municipality Garden Section /D.Balfour & Sons, Location – Al Am, Year of Completion – 1994,

Construction of Bida Hazza and Um AI Asthan Camp Water Supply System Contract No. EC/731

4 Nos 54,809 Gallon Bolted Steel Tanks, 4 Nos 36,600 Gallon Bolted Steel Tanks including foundation, 15.0 K.M 150 mm dia and 4.0 KM 200mm dia ductile iron pipelines, 114 Valve

Chambers, Filtration Plant Pump House, Operators

House, Cold Store, 14 Well Head Shelters including all electro mechanical and instrumentation works which includes Booster pumps, filters, overhead transmission line and all associated civil works including 26,000 m2 of earth work, levelling/grading/compaction.

Client / Consultant – UAE Armed Forces /Engineering Corps, Location – Sweihan, Year of Completion – 1987,

Water Supply System for AI Falah Military Camp Contract No. EC/593

Supply and Construction of 14.0 K.M Ductile Iron Pipeline with all accessories, 10,000 Cu.m Earth Moving.

Client / Consultant – UAE Armed Forces /Engineering Corps, Location – Sweihan, Year of Completion – 1982,

Design & Construction of Water Supply System to Old Sweihan Contract No. EC/564

35.0 K.M. 600 mm D.I. Pipeline, 500,000 Cu.m earth moving, 8 wells complete with well field installations, Generator House, Pumping Station, 3 Nos 1/4 MillionGallon Water Tanks, 3 Nos 500,000 Gallon Tanks, Foundations, Pressure Filters, Electrical and instrumentation Works

Client / Consultant – UAE Armed Forces /Engineering Corps, Location – Sweihan, Year of Completion – 1982,

Design & Construction of Water Supply System to Madina Zayed Contract No. EC/524

2 Nos 1/2 Million Gallon steel Tanks and

Foundations, 90.0 K.M of Ductile Iron Pipelines, 24″ & 20″ 90 K.M access roads, 2,000,000 Cu.m of earth works, R.C. Manholes, Valves, Fittings, Road Crossings, Pumping Stations, Booster Pumps, Electrical and Instrumentation Works.

Client / Consultant – UAE Armed Forces /Engineering Corps, Location – Sweihan, Year of Completion – 1981,

Design & Construction of Water Supply System at Madina Zayed Contract No. EC/502

8 Nos 1 Million Gallon steel Tanks and Foundations, 11.0 K.M of Ductile Iron Pipelines, 24″ & 20″ 110.0 K.M access roads, 10 metres wide 2,500,000 Cu.m of Earth Moving, R.C. Manholes, Valves, Fittings, Road Crossin9s, Distribution Networks including connection to various camps, water filling station, etc

Client / Consultant – UAE Armed Forces /Engineering Corps, Location – Sweihan, Year of Completion – 1982,